Let’s get to work!

Here’s an overview of our Project Tasks.

Current Timeline for Master Plan & Economic Resiliency Plan  

Below is a comparison of the project timeline, as outlined in the initial proposal, with notes on the status of each scope item. Included below is also a list of upcoming tasks associated with each scope item. Continue to page 2/3 for more information regarding a defined timeline for each upcoming task.

Note: Month 1 = February 2024 (the date of initial contract award). August 2024 = month 6

Project Timeline – Proposal vs. Actual

General Timeline for Upcoming Tasks

July 2024 

  • Public engagement results (to date) 

  • Economic Resiliency Plan outline and drafting 

  • Economic Data 

  • Additional Due Diligence 

August 2024 

  • Goals and Objectives (Townshipwide) 

  • Economic Resiliency Plan drafting (contd.) 

  • Township Framework 

  • 2025 Master Plan drafting (contd.) 

September 2024 

  • Future Land Use Plan

    • Future Land Use descriptions

    • Transportation Plan 

    • Coastal Resiliency 

    • Other environmental considerations 

  • Implementation Plan

    • Action Plan/Implementation Matrix 

    • Zoning Plan 

  • Subarea Plan 

October 2024 

  • Subarea Plan Roundtables 

  • Subarea Plan drafting (contd.) 

  • Revisions (as needed)

November 2024

  • Open House #2

  • Full drafts submitted to Township for review

  • Full drafts submitted to Planning Commission for review

December 2024

  • 63-day comment period

February 2025

  • Review of comments received

  • Revisions (as needed)

March/April 2025

  • Adoption process