Let’s get to work!
Here’s an overview of our Project Tasks.
Current Timeline for Master Plan & Economic Resiliency Plan
Below is a comparison of the project timeline, as outlined in the initial proposal, with notes on the status of each scope item. Included below is also a list of upcoming tasks associated with each scope item. Continue to page 2/3 for more information regarding a defined timeline for each upcoming task.
Note: Month 1 = February 2024 (the date of initial contract award). August 2024 = month 6
Project Timeline – Proposal vs. Actual
General Timeline for Upcoming Tasks
July 2024
Public engagement results (to date)
Economic Resiliency Plan outline and drafting
Economic Data
Additional Due Diligence
August 2024
Goals and Objectives (Townshipwide)
Economic Resiliency Plan drafting (contd.)
Township Framework
2025 Master Plan drafting (contd.)
September 2024
Future Land Use Plan
Future Land Use descriptions
Transportation Plan
Coastal Resiliency
Other environmental considerations
Implementation Plan
Action Plan/Implementation Matrix
Zoning Plan
Subarea Plan
October 2024
Subarea Plan Roundtables
Subarea Plan drafting (contd.)
Revisions (as needed)
November 2024
Full drafts submitted to Township for review
Full drafts submitted to Planning Commission for review
December 2024
Open House #2 – December 12
63-day comment period
February 2025
Review of comments received
Revisions (as needed)
April 2025
Approval for Distribution - Planning Commission: April 23
May 2025
Approval for Distribution - Township Board: May 14
Public Comment Period (63 Days): Comment Portal Coming Soon to this Site!
July 2025
Public Hearing (Planning Commission)
August 2025
Adoption by Township Board